The following post is written by Bruce Sharp.
"Bruce Sharp. P. Eng, an energy consultant with 25 years of experience in the Ontario energy industry ".
---
TransCanada Energy (TCE) 900 MW Natural Gas – Fired
Generating Station
Analysis of Cost of Moving From Oakville to Lennox
Bruce Sharp, P. Eng.
Results Summary
Known:
The
following additional costs occur – now or in current dollars – as a result of
moving the project.
- $ 40 million Relocation
- $ 88 million Turbine payment, excess
- $152 million Gas Delivery and Management Services (GDMS)
- $280 million Total
Other:
Other,
unknown costs include some or all of gas pipeline and electrical
interconnection costs and payments made to Ontario Power Generation (OPG).
Known Information
- Relocation costs paid to TCE = $ 40 million.
- Turbine payment of $ 210 million made to TCE.
- Net Revenue Requirement (NRR) drops from $ 17,277/MW/month to $ 15,200/MW/month.
- Ontario Power Authority (OPA) to fully reimburse TCE for Alternative Project’s “Gas Delivery and Management Services … on a flow-through basis and without an adjustment to the Net Revenue Requirement”.
- “The turbine payment as well as covering the gas management costs for the new plant reduces the Lennox Net Revenue Requirement”.
- TCE will receive payments to offset some or all of gas pipeline and electrical interconnection costs and payments made to OPG.
Discounted Cash Flow (DCF) Assumptions
- Nominal generating capacity: 900 MW
- Construction cost, overnight: $ 1.25 million/MW
- Fixed OM&A cost: $ 20,000/MW/year
- Debt: 70% of costs, 20-year term, 7.0% rate
- Equity: remaining 30%
- Inflation: 2.25%
- 20% of inflation applied in escalating NRR
- Capital Cost Allowance: 8%, declining balance basis
- Corporate tax rate: 25%
Other Assumptions
- Turbine payment not repaid to OPA.
- No deemed energy market revenue impact arising from higher contract heat rates.
- GDMS encompasses transport from Dawn to Bath and charges for: storage demand, storage deliverability/injection demand, injection/withdrawal and distribution.
- GDMS cost: $ 1,000/MW/month
- 100% of inflation applied in escalating GDMS costs.
- GDMS Net Present Value (NPV) calculation discount rate of 6%.
Findings – Turbine Payment
This part of the analysis evaluated to what extent the up-front turbine payment from the OPA offsets the impact of TCE receiving lower future NRR payments.If TCE’s equity rate of return (EROR) is assumed to be 11-12% then an up-front payment of $ 210 million would leave TCE generally indifferent to the lower NRR. However the DCF evaluation of the original project with the higher NRR indicates that TCE’s actual EROR would have been in excess of 20%. At a conservative (i.e. low) EROR of 20%, an up-front payment of $ 122 million would leave TCE indifferent to the lower NRR. The turbine payment therefore could have been lower by at least $ 88 million and TCE would have been no worse off with the lower NRR.
No comments:
Post a Comment